Quick Facts about the Central Kentucky Water Supply Solution Water Treatment Plant:

  • 20 million-gallon-per-day water treatment plant in Owen County at Pool 3
  • Construction began June 2008
  • 30.1 mile, 42" underground water transmission pipeline through Fayette (3.84 miles), Franklin (15.37 miles), Owen (0.15 miles), and Scott (10.74 miles) counties. Construction scheduled to begin July 2008
  • 55 percent of the water transmission line route is expected to be in public right-of-ways
  • 45 percent of the water transmission line route is expected to involve private easements (Over 90 property owners)
  • $162-million total project cost
  • Fall 2010 completion
  • Project Contractors:
    • Reynolds-Rogers, LLC of Orleans, Indiana for the Kentucky River Pool 3 Water Treatment Plant and Intake in Owen and Franklin Counties
    • Garney Companies of Kansas City, Missouri for High Service Mains (underground water transmission lines) from the water treatment plant in Pool 3 of the Kentucky River to Kentucky American Water's Central District in Fayette County
    • PAE & Associates of Brookville, Ohio for Booster Pump Station and tank located in Franklin County

For more information contact:
Raymond Golden
Director, Communications & External Affairs
Kentucky American Water
2300 Richmond Road
Lexington, KY 40502
Office 859.335.3662
Fax 859.268.6315
Cell 949.231.0590
Raymond.Golden@amwater.com

 

  © 2009 American Water. All Rights Reserved | Privacy Policy | Terms of Use | Site Map | Powered by SilverTech, Inc. Puddles