To Sprinkler Systems - (Fire Services) To obtain a water supply for a building's sprinkler system it is necessary to apply for a "fire service" from Kentucky American Water. A fire service consists of a main tap, a large diameter service line, post indicator and valve at property line and a theft meter. A stub will be extended a short distance past post indicator for sprinkler system piping tie-in. In applying for a fire service, it is assumed that there is either an existing main in front of the building, or a main extension is planned to provide domestic water service and that main may be tapped. Apply by printing out the Fire Service Application Packet . The packet includes instructions, specifications, two forms to be completed and submitted with five (5) sets of plans to: Kentucky American Water ATTN: Fire Service Specialists 2300 Richmond Road Lexington, KY 40502 Any questions regarding these instructions, please call our Fire Service Specialists at 859.335.3822 or 335.3833. The Process: - Developer, general contractor or sprinkler contractor submits two copies of plans to fire department for hydrant plotting. (See Fire Department Submission List)
- Delivery of application packet and log-in at Kentucky American Water.
- Fire flow test ordered by Fire Service Specialist, test conducted by a distribution crew to determine if flow requested can be met. If fire flow is not met, sprinkler contractor is informed. If fire flow can be met, plans are put in a queue for the fire service design drawing and material listing by the CAD draftsman.
- Once drawn, plans are sent to Project Manager- New Development/Construction (PM) who prepares estimates and agreement for the developer deposit based on average cost and sends them to applicant for deposit.
- At same time, PM sends plans to assigned Fire Service Specialist for field inspection to verify measurements and record any deviations so material may be ordered, bid and installed as designed.
- Following field inspection, drawing is adjusted for variations by the CAD draftsman. If there is a significant design change/cost increase KAW reserves the right to require additional deposit.
- Once agreement and deposit is returned, PM prepares bid and sends to contractors. At the same time material is ordered and will arrive in 4-6 weeks. Approximately 10 days after send-out bids are returned and evaluated.
- Street cut and main blockage permits are prepared and the task order estimated and approved for installation.
- Operations specialist receives confirmation of material arrival date and coordinates construction start with contractor.
- Fire service is installed, chlorinated and flushed as required before being placed in service.
Timeline
It normally takes 2-3 weeks from receipt of request packet until project is designed and agreements and deposit request are sent to applicant. Approximately 4-8 weeks after deposit is received, field inspection is completed and material is ordered, material will arrive. This is approximately a 2 - 2 ½ month process before construction can begin. Delay in the applicant's site being available for field inspection or in applicant making required deposit will increase pre-construction process time. Agreements An Application for Special Connection Agreement for the fire service and if applicable for a private hydrant to establish monthly payment for maintenance and support facilities. |